Saugerties Animal Shelter ( UPDATE 11/7/26)
SIPS- Installation of 1st layer of roofing felt has been completed and sleepers have been installed. Second layer of roofing OSB has commended. Installation of exterior house wrap at SIPS wall panels is occurring. Metal roofing installation to follow.
Interior- SIPS roof panels have been caulked and taped. Wall panels have been caulked.
WINDOWS- Windows have been delivered to site. Installation of windows is to commence after house wrap is complete.
CARPENTRY- Installation of interior sheetrock at bottom side of SIPS roof panels is to commence once second layer of roofing felt is installed.
SITE WORK- Installation of Septic System is to commence mid- November.
HOLLOW METAL- Hollow metal frames have been delivered to site.