05/22/2026
May 12, 13 and 14, 2026 site work was completed for our geotechnical testing. There were 11 trenches dug (6.5 to 8.5 feet deep) for absorption testing and 12 bore holes for compaction testing.
Once HF Lenz receives the test results in June, the project permitting process can begin. It’s anticipated that the permitting process will take 6 to 8 months.
Depending on our fundraising, the plan is to break ground late spring or early summer of 2027, and play ball in fall. Worst case 2028.