10/06/2026
Quick progress update.....
As you can see, Keith's been busy with the red paint inside the frames, which is really looking good in there now. We thought he'd have enough paint to last him a couple of weeks, but it was all used in 1 day!
On the boiler, all the rivets that need removing from the outer firebox are now out, so we can get on with removal of the wasted plate sections and start manufacturing the new ones. As seen in a previous post, some of the steel has already been received so we hope to get on with this job very soon.