04/06/2026
Freshwater Village Project Update
Despite challenging wet weather conditions throughout May, construction continues to progress strongly on Brays Road and across all areas at Freshwater Village.
Key milestones achieved this month include:
✔ Significant progress with the installation of the new water main on Brays Road
✔ The Woolworths roofing installation is nearing completion
✔ Multiple concrete slab pours and polished concrete works
✔ Continued framing, formwork, and loading dock preparation
✔ Advancement of hydraulic, fire, electrical, mechanical, and refrigeration services
✔ Ongoing civil infrastructure, drainage, and trenching works
Our project teams successfully managed weather-related disruptions through proactive planning and work resequencing, maintaining momentum across multiple work fronts.
Looking ahead, June will focus on completing tenancy slabs and foyer works, progressing internal services, continuing civil infrastructure works, and advancing roofing activities within the dining precinct.
A great effort by all project partners and trades involved as Freshwater Village continues to take shape.
Read the full article here: https://www.thehubatfreshwater.com.au/post/freshwater-village-project-update