Sharing a CONSTRUCTION UPDATE from Hawkesbury City Council regarding the North Richmond Community Centre / Youth Centre!
Hawkesbury City Council has engaged Boylson Group to deliver a major upgrade of the Youth Centre at the North Richmond Community Precinct. Once complete, the refreshed facility will provide a modern space for young people and the community to enjoy, while also being able to operate as an emergency evacuation centre when required.
📅 Works have commenced from 19 October 2026 and are expected to be completed by mid-2027 (weather and site conditions permitting).
The first stage of works will include:
✅ Site establishment and fencing
✅ Internal strip-out of the existing hall
✅ Removal of two approved trees
During construction, you may notice:
• Construction activity and occasional noise during work hours
• Trucks entering and exiting the site via William Street
• Temporary changes to pedestrian access within the car park, with all routes clearly signposted
👍 The good news is that the North Richmond Community Centre will remain open throughout the project, with safe pedestrian access maintained at all times.
To minimise impacts on the community, the project team will:
• Schedule the noisiest works outside the Community Centre's busiest times
• Keep construction vehicles, materials and bins within the site
• Use traffic controllers for larger deliveries
• Manage dust and maintain cleanliness along William Street
We appreciate the community's patience and understanding while these important upgrades are carried out and look forward to sharing progress along the way.