06/16/2026
Pool Project Update: Many members have been asking for an update on the pool project, and I wanted to take a moment to share where things currently stand.
Our pool contractor continues to make steady progress and is diligently working through the final phases of the project. One of the unexpected challenges we’ve encountered has been groundwater seeping through a seam in the pool shell. This issue prevented the sealer from bonding properly and delayed the painting process. As of this morning, the contractor advised that the groundwater issue should be resolved this week, allowing paint preparation to begin.
In addition to the pool shell work, significant progress has been made on the mechanical systems. The contractor is nearly finished installing the new equipment for the main pool in the newly constructed equipment room. Once that work is complete, installation of the kiddie pool equipment will begin. The contractor and electrician have remained in constant communication throughout the project to ensure electrical work can proceed immediately behind equipment installation.
This project involves entirely new piping, electrical systems, and plumbing infrastructure. While we anticipated some upgrades, we did not anticipate the number of issues that would be uncovered once work began. Although these discoveries have extended the timeline, they are being addressed correctly rather than temporarily patched. Our goal is not simply to open the pool, but to provide a reliable facility that will serve the Lodge well for many years to come.
The contractor is also coordinating with the project engineer for a site visit and inspection, as well as County Environmental Health and County Inspections, to ensure all work meets required standards before opening.
At this time, I do not have an official opening date to announce. However, I want to assure everyone that the project is moving forward and the pool will open once all work, inspections, and approvals have been completed.
I also want to apologize for the lack of recent updates. Between Lodge responsibilities, work, family, and other commitments, I have not done as good a job communicating progress as I would have liked. I appreciate everyone’s patience, understanding, and continued support as we work through the final stages of this project.
Thank you for your patience as we invest in improvements that will benefit our members and guests for years to come.
Fraternally,
Chris Setzer
Exalted Ruler
Sanford Elks Lodge #1679