Emery Street Sewer Project Update – October 6
Some good news... the sewer replacement itself is now complete from 700 South to Indiana Avenue, and crews are getting closer to wrapping up the road work.
Beginning Wednesday, October 7, crews will dig several test pits between 700 South and Indiana Avenue to make sure the soil above the new sewer line is properly compacted before paving.
Paving is currently anticipated for October 12–16.
For now, Emery Street remains closed to through traffic from 600 South to Indiana Avenue, with no parking in the construction area. Please continue to follow posted detours.
There are several projects happening around Poplar Grove right now. You can find updates on this and other neighborhood construction projects here:
https://www.slc.gov/mystreet/2026/03/13/poplar-grove-projects/
Hopefully we're getting close to having Emery back!
Salt Lake City will complete several construction projects in the Poplar Grove neighborhood during the 2026 construction season, including street reconstruction on Navajo Street and 600 South, bridge work over the Jordan River Trail, and a sewer project on Emery Street.