Parks Board Update: Bark Park Progress and Ongoing Projects
At Tuesday night's meeting, the Sac City Parks, Recreation & Natural Resources Board approved Bark Park rules and regulations, recommending them for city council consideration. The rules have already been reviewed by the city's attorney and insurance carrier. The park will operate on an honor system, with a volunteer sign up sheet planned for periodic maintenance walkthroughs, similar to a Meals on Wheels style rotation. Long term landscaping maintenance will eventually transition to the city parks department.
Once city council takes action at its July 14 and July 28 meetings, signage reading "Bark Park" will be produced through Iowa Prison Industries, with an anticipated opening in early August.
Bark Park progress to date:
Phase 1, fencing and concrete, is complete
Phase 2, waste stations, water fountains, benches, and picnic tables, is underway
Phase 3, agility equipment, is planned for the future
The board recognized the fundraising that has supported the project, including a can drive, a sponsorship memorial wall with plaques and sunshades, and proceeds from a recent wiener dog race.
Treasurer's Report-----
The board reviewed current account balances, including a foundation and state bank account balance of $14,667.31 and a tree fund balance of $530. City council recently approved payment of roughly $2,780 for bridge lumber from the city account, effectively zeroing out this fiscal year's city balance. The board discussed the possibility that a portion of this year's allotment may carry over, and that the city's allotment for the coming fiscal year may increase to approximately $6,000, though neither figure has been confirmed. Community Chest funds designated for the bridge project remain available within the foundation balance.
Other Park and Trail Projects-----
River cleanup crews cleared two obstructions from the river in mid-June.
Lumber has arrived for the Riverview Park walking trail bridges. Installation is pending drier ground conditions in the oxbow areas.
An engineer visited Chautauqua Park and Grant Park to begin site assessment work for future Raccoon River Trail engineering and grant preparation. The board discussed sharing GIS shape file data to support integration of river and trail planning.
The board is considering relocating several mature red oak trees from the tree farm to the primitive campground, with a possible equipment donation from Engle to assist with the work.
The board is looking into a windscreen for the South Park pickleball courts, with cost estimates of roughly $1,000 for screening material. Follow up conversations with players regarding wind concerns were planned for July 8.
Work continues on OHV Park trail development, tire removal, tree planting, and mapping efforts, pending resolved liability questions and contractor availability.
The board also discussed reviving the memorial bridge plaque fundraiser, including a paper order form to be published in the local newspaper, and began preliminary discussion of a future river crossing bridge project.
The board's next meeting is Monday, August 4, at 6:00 p.m.