Eagle Lake Community Association - ELCA

Eagle Lake Community Association - ELCA Eagle Lake Community Association is a gated Recreational Vehicle Community Association.

Eagle Lake Community Association Official Notice – Structure ComplianceDear Eagle Lake Property Owners,Please be reminde...
06/03/2026

Eagle Lake Community Association Official Notice – Structure Compliance

Dear Eagle Lake Property Owners,

Please be reminded that Eagle Lake is a zoned “Recreational Community” and is subject all appropriate zoning rules and regulations.

Key Regulations:
• Each campsite is permitted one hard-top structure (Florida room, screen house, or hard-top gazebo) only.
• The maximum allowable size for any hard-top structure is 12’ x 12’ (144 square feet).

Important Compliance Notice:
Two hard-top structures on any single lot or campsite are not permitted. Property owners currently in violation of this rule must remove the non-compliant structure(s) and bring their property into compliance no later than June 30, 2026. Effective July 1, 2026, any property remaining in violation will receive a PRIM violation citation with a minimum fine of $150.00, and may be subject to additional enforcement actions as outlined in the Eagle Lake Community Association Rules and Regulations.

Additional Covered Space:
If additional covered space is desired, property owners may install one supplementary structure provided it meets the following requirements:
• Maximum size of 12’x 12’ (144 square feet)
• A previously submitted application for permit approval
• Canvas roof only (no hard top)
• Must be removed by November 1st each season

Permit Requirements:
A permit must be approved prior to installation and/or building for any of the following:
• Florida Room
• Hard-Top Gazebo
• Screen House
• Canvas-Topped Canopy Cover

The attached image provides an example of authorized structures.

Variance Requests:
Any structure (hard-top or canvas) exceeding 12’ x 12’ requires variance approval from the Environmental Control Committee. To request a variance, obtain your denied permit and email the committee requesting a variance.

Thank you for your prompt attention and cooperation in maintaining compliance with these regulations. If you have any additional questions please email Kayli at [email protected].

Sincerely,
Eagle Lake Environmental Control Committee
[email protected]

Contractor Spotlight:ACV InvestACV Invest was established in October of 2023.  At ACV Invest Landscaping Services, we ta...
06/03/2026

Contractor Spotlight:
ACV Invest

ACV Invest was established in October of 2023. At ACV Invest Landscaping Services, we take pride in transforming properties with dependable service, professional workmanship, and results that last. For 3 years, we’ve helped homeowners and businesses improve their outdoor spaces with quality landscaping solutions. We work with any budget and help you find the best solution for your project — without compromising on quality.

https://www.facebook.com/share/16xWKD1Qty/?mibextid=wwXIfr

Important Notice:
Eagle Lake is not responsible for work performed by contractors. Homeowners are free to choose any contractor. This contractor has been added to our list after paying a registration fee, attending a meeting with management and the environmental officer, and providing proof of HIC license and insurance.

Eagle Lake Wastewater Treatment Plant – Electrical Upgrades Project Update: June 2nd 2026 We continue to provide regular...
06/02/2026

Eagle Lake Wastewater Treatment Plant – Electrical Upgrades Project Update: June 2nd 2026

We continue to provide regular project updates, supplemented by visual documentation that offers valuable context on the substantial progress being made. Since our last update, significant work has been completed—much of which is not visible from the roadway. We remain committed to sharing detailed written summaries along with high-resolution 4K photographs to keep the community well informed. The attached photos reflect the high level of construction activity currently underway. This update is to focus on the electrical upgrades being done on the waste water treatment plant site in preparation of our three phase project.

On May 15th, highline crews were on site at the treatment plant to prepare the area for the relocation of the overhead high-voltage lines, while also replacing aging wiring and a utility pole. As part of the ongoing three-phase electrical system upgrade, crews have been working diligently to stay ahead of the general contractor’s progress at the plant.

To maintain project momentum, highline crews were temporarily reassigned from Eagle Lake Drive to the treatment plant site on May 15th. That same day, crews installed a new 45-foot utility pole in preparation for relocating the primary high-voltage lines. This work serves two critical purposes: enhancing safety for upcoming crane operations and replacing aging infrastructure that directly serves the plant.

On Monday, May 18th, crews replaced another 45-foot utility pole on Skyview Drive near the entrance of the plant. This pole was configured to accommodate additional wiring and now serves as the junction point feeding the plant and was upgraded from a 40-foot pole. On Tuesday, May 19th, three new primary wires and a neutral wire were installed between the new poles. The new lines were positioned approximately five feet higher than the previous wiring to better accommodate future needs and clear ongoing construction activity.

As shown in the attached photographs, the existing wiring and components have provided reliable service to the community for many years but are now well beyond their expected service life, with visible burn marks present on the primary conductors. Fixing issues such as this helps solve voltage issues throughout our electrical system.

As previously communicated, the treatment plant will be transitioned to a full three-phase electrical system. It is currently served by an open delta configuration, which utilizes two transformers to supply three-phase power. An open delta configuration is used to supply three-phase loads without needing a third transformer. This setup provides approximately 57.7% of the capacity of a complete three-transformer delta bank. This is because the two transformers must handle the full line currents and voltages in a way that doesn’t simply add to their ratings.

As part of this upgrade, once the new primary wires are in place, three new 167 kVA transformers will be installed on the existing utility pole at the corner of the treatment plant building. This has the capacity to deliver over 1,200 amps to the plant. The existing transformers (rated at 167 kVA and 250 kVA) will be retained and stored for emergency use elsewhere in the community as needed.

The final phase of this work will require a brief planned outage at the plant for a few hours to install the new transformers and transition the plant to the true three-phase system. Following the cutover, crews will systematically balance loads across the circuit. This work will be performed during peak usage periods by design to ensure optimal performance and long-term reliability for the community.

We appreciate the community’s continued patience and support as we complete this important infrastructure improvement project.

Should you have any questions regarding this project or other infrastructure initiatives, please do not hesitate to contact us.

06/02/2026
New hours, same great food! Call ahead for Pizza and Wings every Friday at the Eagle Lake Clubhouse. Call anytime 3:00 -...
06/02/2026

New hours, same great food! Call ahead for Pizza and Wings every Friday at the Eagle Lake Clubhouse.

Call anytime 3:00 - 8:00pm to place your order and schedule your pick up time!

Dinner's already waiting for you up at Eagle Lake!

Project Update: Three-Phase Electrical Upgrade- June 1st, 2026We continue to provide regular project updates; however, v...
06/01/2026

Project Update: Three-Phase Electrical Upgrade- June 1st, 2026

We continue to provide regular project updates; however, visual documentation often offers helpful context regarding the significant progress being made. We are pleased to provide the community with an update on our three-phase electrical upgrade project. This initiative will improve electrical load balancing across the community and support both the current and future needs of the wastewater treatment plant.

Since this project began on May 13th, the high-line crews have made substantial progress. While some crew resources were temporarily redirected to address emergency utility pole replacements and critical work at the wastewater treatment plant site (details of which will be shared on June 2nd), the team has continued to advance the main project effectively.

The crews have successfully navigated weather challenges and a holiday weekend, during which we intentionally limited work on major roads to minimize traffic disruption. To date, they have completed the reconfiguration of 16 poles and replaced one deteriorated pole located across from Marina 1 in the WD section. This pole was identified during the initial scoping phase as being in poor condition. It was successfully replaced on Friday, May 22nd. As shown in the attached photos, the original pole was at risk of failure, which could have resulted in a power outage for the surrounding area. The new pole has been installed adjacent to the existing one. Two additional poles were discovered along this route and are under further evaluation for replacement as well before they become bigger issues.

Traffic management has gone smoothly, with only minor detours required. The crews have logged 7 full days on this project thus far, three of which were dedicated to work at the treatment plant site. All on-site activities have been carefully coordinated with the waste water plant contractors and management to avoid any disruption to operations. Crews are currently finishing up on Lake View South in the WD section, but they will have to due some additional work on that road.

We continue to coordinate closely around major deliveries to the wastewater treatment plant to ensure that construction activities and site operations do not interfere with one another, such as the scheduled concrete delivery on May 28th.

The high-line crew is currently ahead of schedule. We are very pleased with the quality of their work and their flexibility in accommodating the broader project schedule. This is a complex undertaking that requires careful planning and real-time decision-making as conditions evolve. No work will be performed the week of June 1st on this part of the project.

Background on the project:
A major electrical infrastructure improvement project is currently underway as of 8am on May 13th. Crews will be installing a third phase of power, by running new high-voltage lines from the intersection of AM Hughes Boulevard and Eagle Lake Drive to the treatment plant.

The project includes stringing new high-voltage lines along 46 existing poles, reconfiguring every pole along the route and replacing several utility poles. Crews will begin with the pole reconfigurations first and replacing the damaged poles and once that is complete, they will begin stringing the new wire. Portions of Eagle Lake Drive and Skyview Drive will experience temporary road closures during this project, with clearly marked detours in place. The work is scheduled to take approximately two to three weeks to complete. Equipment and materials have already been staged at the lake.

Power outages are not anticipated during most of the project. However, a brief planned interruption will occur on the final day when the new high-voltage line is tied into the existing grid. Minor, short-duration disruptions are also possible during utility pole replacements. Crews will make every effort to perform live wire transfers to minimize impacts.

As part of this project scope aging equipment will be replaced, trees will be trimmed as needed and poles will be shored up better if need be by adding new guy wires. Also once the plant is tied in, the high line crews will go back and balance out the sections along the route for improved power delivery.

We are coordinating closely with the high-voltage contractor, who is currently managing several priority projects for us, including emergency pole replacements. The contractor is mindful of community needs and peak usage periods and is committed to minimizing disruptions to daily operations. Both the high voltage contractor, electrical contractor, and linemen have been on site several times for project meetings and ensuring they have all materials needed and understand the scale and scope of this project. Please note that weather conditions may affect the project schedule.

This upgrade is essential to provide sufficient power capacity to the treatment plant and will significantly reduce the electrical load on lines serving the surrounding area.

Detour maps have been prepared and will be posted in advance of construction activities. The detours are designed to maximize crew safety and efficiency while minimizing inconvenience to the community. Every effort is being made to limit impacts on residents and local traffic.

We appreciate the community’s continued understanding and support as we work to complete this important infrastructure improvement.

05/30/2026
Weather Watch-High Winds
05/29/2026

Weather Watch-High Winds

Important Wildlife Update for the 2026 Season:As we begin the 2026 season at Eagle Lake, we would like to share importan...
05/29/2026

Important Wildlife Update for the 2026 Season:

As we begin the 2026 season at Eagle Lake, we would like to share important information regarding our local wildlife. Our community is home to diverse and beautiful wildlife, and it is our shared responsibility to preserve it in a safe and sustainable manner.

2025 Bear Activity:
Last year, the community experienced three close encounters with black bears, two of which required intervention by the Pennsylvania Game Commission. One incident resulted in an arrest of an individual by local law enforcement at the pool complex. One of the events the bear made its way through the mini golf course at the clubhouse and all the way to the lower parking lot right after the 9/11 memorial service. These events underscore the importance of proper wildlife management.

We strongly remind all residents that feeding any wildlife is prohibited and is detrimental to both the animals and the community. Feeding wildlife on Eagle Lake amenities will result in a citation and referral to the Pennsylvania Game Commission, with Eagle Lake fines starting at $100. Feeding on private property will also be reported. Several residents were cited for this violation in 2025 as tips came in through the game commission itself.

The Pennsylvania Game Commission actively discourages feeding deer and other wildlife, as it can lead to the rapid spread of fatal diseases such as Chronic Wasting Disease (CWD), disrupt natural foraging behaviors, cause digestive problems, and attract dangerous predators closer to residential areas. What may seem like a kind gesture ultimately does more harm than good.

Fawn Safety Reminder:
We are seeing an increase in human-related incidents involving fawns. If you encounter a baby deer, please leave it alone. It is illegal in Pennsylvania to possess, handle, or attempt to domesticate wild fawns, with fines reaching up to $1,500 per animal.

Mother deer frequently leave their fawns unattended for extended periods as part of their natural “hider strategy.” A fawn found alone in tall grass, near homes, or under vehicles is rarely abandoned. Touching or moving a fawn can transfer human scent, potentially causing the mother to abandon it or attracting predators.

Additional Guidance:
• Never feed fawns cow’s milk or human food, as it can cause severe illness or death.
• Adult animals often leave their young while foraging and typically return shortly after.
• Two fawn fatalities have already occurred this year believed to be linked to human interaction.

Bear with the Injured Leg:
The bear with the previously broken leg has been monitored in the area for approximately two years and continues to survive. While these situations can be emotionally difficult, they are part of natural wildlife behavior. This bear is more aggressive as he is at a disadvantage. Don’t be fooled that he is just sitting there, injured animals behave different. Community staff maintain regular communication with the Pennsylvania Game Commission and notify them promptly of any concerning situations. The game commission has been in for this to show face due to an increase in calls. The bear will remain as nothing can be done in this situation.

Community Protection Measures:
Eagle Lake has implemented non-lethal measures to deter bears from dumpsters and reduce risks to residents. These measures are deployed only by authorized staff. In cases where non-lethal methods are unsuccessful and there is an immediate threat to human safety, lethal action may be taken as a last resort by the appropriate officials which we do not want to see happen. When a bear feels boxed in it will behave differently especially when cubs are present.

Zero Tolerance Policy:
A zero-tolerance policy is now in effect for all wildlife feeding and interference. This policy applies equally to residents and staff. We kindly ask all residents to observe wildlife from a distance and refrain from feeding, baiting, harassing, or interacting with animals. This includes sitting at the dumpster sites. Attached are photographs of Eagle Lake wildlife for your enjoyment. Using these images helps minimize unnecessary human-wildlife interactions that could ultimately lead to the removal of animals from the community.

Thank you for your cooperation in protecting our community’s wildlife and maintaining a safe environment for all.

Effective June 5, 2026!!
05/29/2026

Effective June 5, 2026!!

Address

15 Am Hughes Boulevard
Moscow, PA
18444

Alerts

Be the first to know and let us send you an email when Eagle Lake Community Association - ELCA posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Organization

Send a message to Eagle Lake Community Association - ELCA:

Share