06/17/2026
RV-12iS Build Update:
Week 118: With the first day of summer approaching, many of our youth builders were on road trips or involved with local activities. Never the less, our volunteers and one builder picked up where we left off the prior week. The day began by removing the wings that we attached for display at our monthly breakfast and placing them back in their rack. With all the work remaining inside the fuselage, walking 11 and 1/2 feet around each wing would have been a major inconvenience! The tailcone fairing team continued their work drilling, trimming and sanding the lower half of the fairing. The upper half was then trimmed and sanded for best fit with the lower half. Offset lines for the mating surfaces were then laid out as well as nutplate locations. With both halves attached to the tailcone, both halves were match drilled to #40. Nutplates were then attached to the upper half with flush squeezed rivets. With both halves held in place with #6 machine screws, marks for final sanding were laid out to produce an even gap at the faying surfaces. Fastener holes for the upper half were machine countersunk and the two halves were again assembled with #6 machine screws. And over in the corner, our one builder continued applying a carbon fiber adhesive film to the center and right seat instrument panel.
On the forward side of the firewall, generator A and B ground cables were attached to the Rotax fuse box lugs and to the firewall. Next, the Rotax starter relay wire had to be routed through an existing insulating boot on the relay and shared with another wire on the same mounting lug. When that was complete, another cable was attached to the master relay, two HIC cables were connected to the Rotax ECU, and the IS BUS connector was secured to the instrument panel shelf. On the aft side of the firewall, main and auxiliary fuel pump cables in the main harness were routed through the firewall and instrument panel shelf to be connected with corresponding Rotax ECU harness followed by another firewall ground cable installation. And lastly, both center and right seat instrument panels with their carbon fiber film, radios, and displays were installed.
Week 119: This week the morning session began work on both ends of the plane. In the rear of the plane, the tailcone team continued work trimming and fitting the two halves to establish the correct clearance between it, the rudder, and the stabilator. Working in three dimensions, too much of a trim in one plane effects the clearance and fit in another. On the top half, a hole had to be cut in the correct location to provide clearance for the rudder horn, while on the bottom half, another clearance hole had to be cut to provide clearance for the trim/servo assembly. When finished, a clearance of 1/8” had to be maintained between all moving parts and the control surfaces. Needless to say, the tailcone was installed, marked, and trimmed multiple times.
In the cockpit, another team was trimming, routing and attaching the control cables for the heater vent doors. These doors are located on the firewall, underneath the instrument panel, and behind the control pedals. With very limited room and visibility, it was necessary to switch between workers to avoid fatigue. Even with two workers, the entire morning session was required to install only the right seat cable. While that was being done, the fuel hose between the filler cap and the tank was installed. Once completed, the last few rivets securing the tailcone to the fuselage were pulled.
The afternoon session began work on the left seat heater vent doors. Although we learned a lot from the previous installation, it was still very time consuming and brutal for the builders. We will finish it up next week. We did however manage to install the upper forward fuselage skin, the right seat instrument panel and display screen, and the access panels on the cockpit floor.
Vince Miraldi