Hampton Creek Barrier Repair Update
Work is officially underway on the Hampton Creek barrier repair project!
Contractors from Baker Construction are currently onsite and actively working under contract with the Tennessee Wildlife Resources Agency (TWRA). Crews are in the process of diverting stream flow around the barrier so that repairs can safely begin.
Once the diversion is complete, construction will move into the barrier repair phase. The project is expected to be completed within the next 60 days.
A special thank you to Barry Heller, who captured today's video while enjoying a day of fishing on Hampton Creek. His footage provides a great look at the progress being made on the project.
We appreciate everyone's patience during construction and look forward to sharing additional updates as the work progresses.