08/27/2026
While the Trail is Closed
the SVTC is Busy Maintaining the Trail.
A few weeks ago a sink hole developed over one of our drainage areas in the closed section of trail below Kennywood An old corrugated steel drain pipe had rusted away and collapsed under the trail. Our volunteers spend about 200 hours digging out the collapsed drain pipe and replacing it with a new plastic 18 inch drain pipe. Our new excavator and other vehicles were essential in this project.
West Mifflin supplied a metal plate so that their water treatment trucks could continue to drive on the trail to get to their plant below the Phantom’s Revenge rollercoaster. The West Mifflin Public Works Department is going to asphalt pave over the new drain pipe.
When the trail reopens you will be able to bike over a new 18 inch drain pipe. This was one of the bigger projects we have completed saving thousands of dollars by not engaging a company to replace this collapsed drain pipe.