Wallace SC - Old Wire Road Bridge update # # #Per SCDOT Daniel Flowers. Old Wire Road is now OPEN to public.
04/22/2025

Wallace SC - Old Wire Road Bridge update # # #
Per SCDOT Daniel Flowers. Old Wire Road is now OPEN to public.

Wallace SC - Old Wire Road Bridge update # # #Per email from SCDOT Project Manager, Tony Edwards: Street signs are going...
04/14/2025

Wallace SC - Old Wire Road Bridge update # # #

Per email from SCDOT Project Manager, Tony Edwards: Street signs are going up this week and the bridge will be open for public use on Friday, April 18th!

Wallace SC - Old Wire Road Bridge update # # #Bridge is done!!  cleanup, guard rails, and pavement are all that’s left.
11/03/2024

Wallace SC - Old Wire Road Bridge update # # #

Bridge is done!!  cleanup, guard rails, and pavement are all that’s left.

09/15/2024

Old Wire Road- Wallace SC bridge replacement in the final stages.

09/04/2024

The new Old Wire Road Bridge is progressing quick. Check out the progress below!

The old Dam was abandoned by the owners and the creek will no longer be dammed up. Free flowing creek / pond with a 1 to 2 foot cutout underneath will make the underlying water remain at lower levels than before.

07/10/2024

The new Old Wire Road Bridge being constructed will be up to 4 higher than the previous one to help protect from washout (local crew source).

The old Dam was abandoned by the owners and the creek will no longer be dammed up. Free flowing creek / pond with a 1 to 2 foot cutout underneath will make the underlying water remain at lower levels than before.

Old Wire Road Bridge replacement is moving quickly. Click through these timeline shots! March 2024 - July 2024
07/10/2024

Old Wire Road Bridge replacement is moving quickly. Click through these timeline shots!

March 2024 - July 2024

March 4, 2024 - Construction officially started: Guard rails down, demolition has begun. Old Wire Rd, Wallace SC - Dam r...
03/08/2024

March 4, 2024 - Construction officially started:
Guard rails down, demolition has begun.

Old Wire Rd, Wallace SC - Dam removal, bridge replacement.

———————————

Feb 15, 2024- Six years later, work Is finally starting. According to crews onsite today, construction willl begin next month.

****************************************
SCDOT Update:
Proposed S-165 (Old Wire Rd) Bridge replacement over Wolf Creek (McMeekin Millpond) in Marlboro County, SC

Project timelines have been extended due to issues with securing additional Right-of-way. The new bridge and supporting structures will be wider and will be redesigned requiring right-of-way from property owners impacted. This is not the same as property owners abandoning the Dam. That was secured the earlier part of 2023. The Right-o-way issue crept up over the summer and has now been resolved.
*********************

As of October 31, 2023 - The right of Way has been resolved.

Project is scheduled to be letted (receiving bids) in December 2023.

Contractor awarded and Project to start March 2024.

Project will be completed by March 2025. (1 year)

Source: (Verbal) Tony Edwards ([email protected]) or Phone (803) 737-1238

Feb 15, 2024- Six years later, work Is finally starting. According to crews onsite today, construction willl begin next ...
02/15/2024

Feb 15, 2024- Six years later, work Is finally starting. According to crews onsite today, construction willl begin next month.

****************************************
SCDOT Update:
Proposed S-165 (Old Wire Rd) Bridge replacement over Wolf Creek (McMeekin Millpond) in Marlboro County, SC

Project timelines have been extended due to issues with securing additional Right-of-way. The new bridge and supporting structures will be wider and will be redesigned requiring right-of-way from property owners impacted. This is not the same as property owners abandoning the Dam. That was secured the earlier part of 2023. The Right-o-way issue crept up over the summer and has now been resolved.
*********************

As of October 31, 2023 - The right of Way has been resolved.

Project is scheduled to be letted (receiving bids) in December 2023.

Contractor awarded and Project to start March 2024.

Project will be completed by March 2025. (1 year)

Source: (Verbal) Tony Edwards ([email protected]) or Phone (803) 737-1238

01/10/2024

Apply now for our summer 2024 class!

Celebrate National Law Enforcement Appreciation Day by telling an officer Thank you!Thank you for all you do! These are ...
01/09/2024

Celebrate National Law Enforcement Appreciation Day by telling an officer Thank you!

Thank you for all you do! These are just some of the local, state, and Federal agencies logos protecting and serving in South Carolina.

Address

Cheraw, SC

Alerts

Be the first to know and let us send you an email when Project Safe & Bright, Inc posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Organization

Send a message to Project Safe & Bright, Inc:

Share