03/22/2026
2026 Pumping Season is scheduled to start the day after Memorial Day, May 26th. The new Pump Station will be tested and commissioned the week prior-May 18th-22nd. A few items remain to be completed-two sections of safety railing on the original lower intake deck, final coating on the lift pipe as it leaves the new pump station and electrical connections in the main power breaker to the new station, and 60' canl actuator valve. Photos show the new Pump Station to the south of the original Pump House with the three 200 HP motors attached to submersible pumps below in the wet well. Electronics including the varible frequency drives are located in the metal cabnet to the east. A steel canopy & ventilated sides will be installed later this summer. The intake headgates will be opened soon to allow the intake to flush out before closing the south discharge gate to bring the intake water level at the pump station to about 8 feet.