The GDCA wants to pass along a message from the contractor leading the roadwork in the neighborhood:
"With our concrete ramp removal and replacement coming to an end, we will now turn to the major aspect of the job of removing the existing asphalt, then applying a new 2-inch lift of asphalt in its place. We’ve handed out flyers during our concrete work and will do so at each street prior to our work beginning. Once we are scheduled, residents will need to have their vehicles moved from the roadway by 8 am and can return at 5 pm. It's a slight inconvenience, but will expedite the process substantially. Please see our anticipated schedule below.
Milling (Removing existing asphalt)
Paving (Installing new asphalt)
Patching (Installing an asphalt patch at failures in the milled surface)
April 15 - Milling Cherokee Ave
April 16 - Milling Cherokee Ave / Drehr
April 17 - Milling Drehr
Weekend
Weekend
April 20 – Patching Cherokee / Drehr
April 21 – Milling Kleinert
April 22 – Milling Kleinert
April 23 – Milling Kleinert
April 24 – Patching Kleinert
Weekend
Weekend
April 27 – Paving Cherokee Ave
April 28 – Paving Cherokee Ave / Milling St. Rose & 100 oaks
April 29 – Paving Drehr / Milling 100 Oaks & Perkins
April 30 – Paving Drehr & Kleinert / Milling Perkins
May 1 – Paving Kleinert / Patching Perkins
Weekend
Weekend
May 4 – Paving Kleinert
May 5 – Paving Kleinert
Remainder of paving will take place the week of May 11
We will keep everyone updated on any delays regarding the schedule."