PROJECT TRACKER PROJECT TRACKER; We bring to you, projects, programmes, and Achievements of His Excellency, Pastor Umo Eno's Administration. Pls Stay tuned....

02/10/2026

Project Tracker's Update...

Nsik Oil & Gas has received Compressed Natural Gas (CNG) equipment in Esit Eket, Akwa Ibom State, as efforts to expand access to cleaner and more affordable energy alternatives continue. The development is expected to support CNG infrastructure and contribute to the growing adoption of natural gas for transportation and other applications.

​ ​ ​ ​ ​
​.

‼️ PROJECT TRACKER'S UPDATE…A’IBOM STATE GOVT FLAGS OFF CONSTRUCTION OF IKOT EKPENE INTERNATIONAL MARKETAkwa Ibom State ...
30/09/2026

‼️ PROJECT TRACKER'S UPDATE…

A’IBOM STATE GOVT FLAGS OFF CONSTRUCTION OF IKOT EKPENE INTERNATIONAL MARKET

Akwa Ibom State Governor, Pastor Umo Eno, has officially unveiled the design and performed the turning of the sod for the construction of the Ikot Ekpene International Market, describing the project as a strategic investment in trade, employment and economic opportunities for the people.

The event, held on Wednesday, September 30, formed part of activities marking the 39th anniversary of Akwa Ibom State and took place in Ikot Ekpene Local Government Area.

Follow us on all our social media platforms for more updates.


29/09/2026

‼️ PROJECT TRACKER'S UPDATE…

‼️Follow up Inspection by the Governor on
the Uyo Village Road erosion control, land reclamation and bridge construction project.

♦️INITIATED BY: His Excellency Pastor Umo Eno, Executive Governor of Akwa Ibom State..

♦️CLIENT: Ministry of Works and Fire Service, Government of Akwa Ibom State.

♦️CONTRACTOR: AMITECH Construction.

♦️CURRENT STATUS OF WORK/ BENEFITS: Construction of bridge.
The intervention will reclaim over 150 hectares of land, protect nearby public facilities and open up the area for the planned Uyo Downtown development, including residential estates and other infrastructure.

♦️PHOTO CREDIT: Project Tracker Media Team.

♦️INSPECTION TEAM LED BY: Excellency Pastor Umo Eno Ph.D. Governor of Akwa Ibom State.

Follow us on all our social media platforms for more updates.

28/09/2026

‼️ PROJECT TRACKER'S UPDATE…

‼️ Follow Up, On Construction of 2.2km tabernacle road & it’s Environs with 0.97km discharge Drain in uyo..

♦️CURRENT STATUS OF WORK AT SITE TODAY :

1. DEMOLITION of a story building is ongoing at Afaha Ube which was a major blockage to the continuation of the 12meters below ground level underground drainage.

2. Ongoing casting of top slabs.

3. Ongoing iron work on manhole and formation of new base iron works.

4. Continued maintenance of the section of Calabar-Itu main road by the site until suitable weather for Asphalting.

♦️CONTRACTOR: Nsik Engineering Ltd.

♦️CLIENT: Ministry of Works and Fire Service, Government of Akwa Ibom State.

♦️ PROJECT INITIATED BY: His Excellency Pastor Umo Eno, Executive Governor of Akwa Ibom State..

♦️PHOTO CREDIT: Project Tracker Media Team.

♦️INSPECTION TEAM LED BY: Michael James
Follow us on all our social media platforms for more updates on this Project.


‼️ PROJECT TRACKER'S UPDATE… ‼️ Follow Up, On Construction of 2.2km tabernacle road & it’s Environs with 0.97km discharg...
28/09/2026

‼️ PROJECT TRACKER'S UPDATE…

‼️ Follow Up, On Construction of 2.2km tabernacle road & it’s Environs with 0.97km discharge Drain in uyo..

♦️CURRENT STATUS OF WORK AT SITE TODAY :

1. DEMOLITION of a story building is ongoing at Afaha Ube which was a major blockage to the continuation of the 12meters below ground level underground drainage.

2. Ongoing casting of top slabs.

3. Ongoing iron work on manhole and formation of new base iron works.

4. Continued maintenance of the section of Calabar-Itu main road by the site until suitable weather for Asphalting.

♦️CONTRACTOR: Nsik Engineering Ltd.

♦️CLIENT: Ministry of Works and Fire Service, Government of Akwa Ibom State.

♦️ PROJECT INITIATED BY: His Excellency Pastor Umo Eno, Executive Governor of Akwa Ibom State..

♦️PHOTO CREDIT: Project Tracker Media Team.

♦️INSPECTION TEAM LED BY: Michael James
Follow us on all our social media platforms for more updates on this Project.


26/09/2026

‼️ PROJECT TRACKER'S UPDATE…

Follow Up on the Ongoing 0.97km discharge Drain at Afaha Ube off Tabernacle Road in uyo.

Current Status of Work: CASTING OF THE LAST SLAB BEFORE ANOTHER DEMOLITION COMMENCE..

♦️CONTRACTOR: Nisk Construction Engineering Ltd.

♦️PHOTO CREDIT: Project Tracker Media Team.

♦️INSPECTION TEAM LED BY: Michael James.

Follow us on all our social media platforms for more updates on this Project...


‼️ PROJECT TRACKER'S UPDATE…Follow Up on the Ongoing 0.97km discharge Drain at Afaha Ube off Tabernacle Road in uyo.Curr...
26/09/2026

‼️ PROJECT TRACKER'S UPDATE…

Follow Up on the Ongoing 0.97km discharge Drain at Afaha Ube off Tabernacle Road in uyo.

Current Status of Work: CASTING OF THE LAST SLAB BEFORE ANOTHER DEMOLITION COMMENCE..

♦️CONTRACTOR: Nisk Construction Engineering Ltd.

♦️PHOTO CREDIT: Project Tracker Media Team.

♦️INSPECTION TEAM LED BY: Michael James.

Follow us on all our social media platforms for more updates on this Project...


25/09/2026

‼️ PROJECT TRACKER'S UPDATE…

Iron Work is ongoing with full force at 0.97km discharge Drain off Tabernacle Road in uyo.

By Nisk Construction Engineering Ltd.

♦️PHOTO CREDIT: Project Tracker Media Team.

♦️INSPECTION TEAM LED BY: Michael James
Follow us on all our social media platforms for more updates.


Address

Uyo

Telephone

+2348023455447

Website

Alerts

Be the first to know and let us send you an email when PROJECT TRACKER posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Shortcuts

Share