I have received a further update from Limerick City & County Council regarding the ongoing N69 Clarina to Court Cross pavement works.
The main pavement overlay works are now targeted for completion this Saturday, 5th September. The contractor is working both day and night shifts this week in an effort to complete this element as quickly as possible.
Once the overlay is completed, a civil works contractor will carry out road verge improvement works. These will be shorter-duration works, with greater control over ensuring they are off the road during the morning and evening peak periods.
The final stage will involve line marking and road stud works, with the overall scheme expected to be completed by the end of September.
The works have now moved west of Ferry Bridge, and are causing significant traffic delays, particularly during the evening peak.
The Council is continuing to engage with the contractor to improve traffic movements and to maximise works during off-peak hours to reduce disruption as much as possible.