14/06/2026
The team were hard at it for the normal 3 days this week .
Tuesday, we started work in lovely bright sunshine, this soon changed to monsoon style rain, then bright sunshine again and then more rain we were trying to fill the 36-ton crane boiler up a to start getting ready to steam test for inspection the team finally achieved this taking all morning between the rain.
We tightened all the mud holes again then lit up warming it slowly and finally into steam, then another session nipping up the mudhole doors, just before it made steam we discovered the pressure gauge was missing so we went to find and fit it and brought the boiler into steam a few small leaks to be rectified, by the end of the day we had tested the safety valves as well all ok we can move on now.
The team removed the petticoat pipe from the smokebox of 4253 to drill the splitter bracket fixing holes and open the fixing holes to the correct size as well, when this was all done a quick rub down of the petticoat pipe and the new bracket, then a coat of heat resistant paint on both bits it’s now ready to put back up to allow all the oil supply pipes to be bent and trial fit ted .
The bunker for 5164 still had all the water we put in at the weekend so we drained it out so we can now finish the painting and fit the access covers on the top coal floor .
Team crinoline were filling and rubbing down the drivers side elephant ear top and bottom sections then welded the last bit on then repainted it , the fireman’s side was fitted on the boiler and the bands put on as well , the driver’s side is rubbed down and primed ready for filling and then it will go up on the loco. The top plate was painted and will be put up hopefully this week before the topping out ceremony takes place; the bunting is all ready to be put up as well .
Friday , we returned to the bunker of 5164 and started the final rub down so we can complete the painting everything was rubbed down, we touched up the undercoat where necessary after we had done the few repairs that were required where people had been climbing in and out ,so we are now ready for the final coat to be applied, the bunker will be then completed and it can make its way in the world .
Work on the crane was completed by draining and resealing the mud hole which had a small leak it will be filled at the weekend and retested ready for the boiler inspector to come ant test.
The firebar bearer brackets returned from the machining that has been done so the brackets are now in place and fit perfectly ,we made a new stud box as the one that used to be at Rolvenden everyone had seen it but no one could find it, so we can now fit all the foundation ring studs .
The last of the crinolines were filled then rubbed down and painted there all ready to go up along with the firebox top sheet as well, we did some work on the lubrication pipe cove that fits on the smokebox by cutting to semi circles out to fit over the rivets around the smokebox .the petticoat pipe was put back up with the new splitter bracket and oil splitter bolted in place so the pipework can be completed .
Sunday, the team continued with various things today including continuing work on the main steam pipe glands cutting all the bits to fill the small gaps due to the shape of the pipes, then the fireman’s unit was put back on the loco as we need to weld the filling bits in situ to avoid any distortions of the pipe .
We started to make the patterns for the bespoke firebars for the new rocking grate we cut up the sheets the were taken to the carriage and wagon dept for final cutting on their saw bench .
While all this was going on the 36-ton brake down crane boiler was being refilled after we had tested it last week and had a leaky mudhole door which was removed and refitted .
Thanks to everyone who came along to help keep it all moving forward to nearer completion .