Wisloe Garden Village Plan, why it is WRONG

Wisloe Garden Village Plan, why it is WRONG The Wisloe Area has 17 homes at present. And Slimbridge Parish approx. 500

Just some of the reasons Wisloe should not be destroyed to build Wisloe Garden Village especially as it keeps getting bigger, up to 1500 then over 1500 now 1500 to 5000 houses.

19/04/2026

Update on the refund of the original ALC which proved to be either highly inaccurate or ?

Question: getting on for 6 years since the ALC survey was supposedly carried out, unseen by anyone here, by Soil Environment Service and still no word of a refund or of any action?

Answer: We have liaised with the relevant service area who have confirmed that The Ernest Cook Trust (the major landowner) has taken the matter up with the company concerned and therefore the issue remains unresolved.

So basically no answer

In 2025 they said
there had been no settlement finalised to date, nothing was held in respect of an update on this matter. However, we were able to advise under Section 16 of the Freedom of Information Act - Duty to Assist - that discussions around this matter were continuing, with the intention of reaching a future resolution. Though it was caveated that, as this was a fluid and ongoing matter, we were unable to provide any indication of when a resolution may be reached.

In 2022 I asked

1 What did this ALC cost GCC

Answer: £705 excluding VAT

2 What is GCC doing to a, recover these costs and b, to find out what happened, was this faked or incompetence?

Answer: GCC jointly commissioned the Soil Environment Services to provide an Agricultural Land Classification. A member of the project team has taken matters up with the company concerned and GCC will benefit from its share of any settlement agreed.

19/04/2026

Update

How has GCC spent on the Wisloe Dev?

2018 £15,517.20
2019 £36,966.71
2020 £41,603.69
2021 £87,856.19
2022 £56,595.21
2023 £67,437.64
2024 £37,037.87
2025 £18,497.46 So far, I guess they don't have all the figures in yet.

So over £361,511.97

27/03/2026

Just found this on the examination library

Stroud District Local Plan Review Examination
Inspectors: Victoria Lucas LLB MCD MRTPI and
Yvonne Wright BSc (Hons) DipTP MSc DMS MRTPI
Programme Officer: Charlotte Glancy
Email: [email protected]
Tel: 07519 628064

___________________________________

For the attention of:
Stroud District Council
National Highways
Gloucestershire County Council
South Gloucestershire Council

Sent by email
25 March 2026

Dear Sir/Madam

STROUD DISTRICT LOCAL PLAN REVIEW EXAMINATION

INSPECTORS’ ADDITONAL QUESTIONS RELATING TO MATTER 11 AND THE LATEST EVIDENCE PUBLISHED BY NATIONAL HIGHWAYS (JUNE 2025)

1. Further to our letter of 18 February 2026, we now invite National Highways, Gloucestershire County Council, South Gloucestershire Council and Stroud District Council to respond to our additional questions relating to the Council’s letter dated 11 July 2025, and the submission of three technical reports on the Strategic Road Network (SRN) published by National Highways.

2. We are only consulting with these organisations at this time, as the evidence relates specifically to those issues discussed during the focused hearing session on Matter 11: Strategic Transport, held on 23 March 2022. The purpose of our additional questions is to aid our understanding of this new technical evidence and to provide clarity on the respective positions of each organisation as regards any implications for the Stroud District Local Plan Review (the Plan). Accordingly, we invite the above organisations to respond to our additional questions, set out their position on the updated evidence and confirm whether any additional highway improvements would be necessary to accommodate planned growth set out in the Plan (in relation to both the strategic and local road network)?

3. As stated in our previous letter, this consultation exercise will be via an exchange of written evidence. We feel that is the most appropriate way forward, at this stage, due to the technical nature of the evidence, and will be sufficient to enable us to understand the positions of the respective parties on the SRN issues.

4. We will therefore not be accepting representations from other organisations or participants at this time. Any such responses received will be returned by the Programme Officer. Depending on the responses received to our questions from the organisations set out in paragraph 1 above, we will of course keep this decision under review, along with whether there will be the need for further oral hearing sessions in the future.

Preliminary Points

5. In the interests of clarity, the National Highways reports that we refer to in our letter are: M5 Junction 12 Stroud District Local Plan Capacity Assessment June 2025; M5 Junction 13 Stroud District Local Plan Capacity Assessment June 2025; M5 Junction 14 Stroud District Local Plan Capacity Assessment June 2025. These reports are available to view on the Examination website under the Programme Officer Update published 13 August 2025.

6. The reports state that local highway network capacity issues have not been considered as part of the assessments and highlight that this needs to be brought to the attention of Gloucestershire County Council and the relevant District Councils. Nevertheless, throughout the reports the impact of traffic growth on the local highway network has been observed and flagged as a concern and congestion is described as ‘significant’. For example, the J14 report highlights that whilst the interim scheme would satisfy National Highways’ interests as regards J14 capacity, it would ‘result in significant adverse impact on the A38 and B409 local highway network’. We need to ensure we fully understand such issues.

7. In our letter to Stroud District Council, dated 24 October 2023, we referred to the potential need for additional modelling and requested that comments should include impacts on both the SRN and local network and whether any further modelling or technical work needed to be undertaken. The issue of traffic impacts on the local road network is therefore an issue that we have previously referred to and have requested additional information where relevant.

Our Questions on the Evidence Base

8. It is our understanding that the modelling originally undertaken to support the delivery of all the Plan’s proposed growth was prepared on the basis that it would be necessary for large-scale junction mitigation schemes for M5 J12 and J14 to be implemented during the Plan period, as set out in the Infrastructure Delivery Plan (IDP). For instance, a grade-separated roundabout scheme at J12 of the M5 motorway would need to be implemented and operational by 2030.

Q1: Is our understanding correct?

9. Subject to specific modifications to the Plan and interim SRN measures, the National Highways’ reports identify that large-scale improvements to J12 and J14 would no longer be required to be implemented during the Plan period. This would result in around 70% of the proposed housing growth being delivered rather than all the planned growth.

Q2: In your view, if the motorway junction improvements are not delivered in advance of the planned growth, has the impact on the local highway network been adequately assessed?

Q3: Would the exclusion of site allocations from the Plan (G1, G2 and PS30) be justified to delay the requirement for the J12 improvements to beyond 2040 (the end of the Plan period)? Would this give rise to any unforeseen impacts or consequences that we need to be made aware of specifically in relation to transport? (We are aware that there may be other non-transport related consequences that would need to be considered separately to this consultation).

Q4: If these SRN mitigation schemes are not necessary to bring forward around 70% of the planned housing growth, does this change the assumptions underpinning the wider traffic modelling, specifically in relation to the local highway network?

Q5: In your view, does the modelling need to be revised and/or further evidence produced so that the impacts of planned growth on the local highway network (without the large-scale junction schemes and including the potential removal of three key site allocations) can be fully understood, to inform our considerations as to whether the Plan is sound? If so, what would be required and what would be the anticipated timeline for completing any such work.

Q6: How could any local highway network impacts identified be resolved via the planning system? For example, any impacts arising from delaying J12 improvements to beyond 2040 and implementing the Charfield scheme at J14?

10. The J12 report identifies significant congestion at the Cross Keys roundabout located
to the west of J12.

Q7: What improvements are planned at the Cross Keys roundabout, when are they proposed to be implemented and how would they impact on the operation of J12 and the local highway network? Has this been considered in the traffic modelling?

11. We understand that J13 can accommodate the planned growth identified within the submitted Plan, in line with the mitigation identified in the IDP.

Q8: Is our understanding correct and do you agree with this statement?

12. The J14 report refers to National Highways accepting an interim scheme for improving the junction, in connection with the Charfield planning application. This would allow for planned growth to be accommodated at J14 without the need for a grade
separated junction.

Q9: Do you agree that the interim Charfield scheme at J14 will allow for planned growth to be accommodated at J14 without the need for a grade separated junction?

Q10: Are there any other effects arising from the implementation of the Charfield scheme that we should be made aware of, such as any impacts arising on the local road network that could be severe in your view? If so, how could these be dealt with through the planning system?

13. Our overarching questions are:

Q11: It would help us if you can summarise and confirm your positions in relation to J12 and J14 and the junction improvements that are necessary to bring forward the planned growth, and specify timelines for implementation?

Q12: Are there any specific schemes or programmes that you consider are necessary and should be included in the IDP?

Q13: In your view have transport impacts (such as congestion) on the local highway network been adequately assessed and understood taking the new SRN evidence into account? Is there a need for further modelling or any other assessment/study? If so, please explain what would be required and the
anticipated timeline for completing any such work.

Q14: Could any local highway network impacts identified be resolved via the planning system and if so, how? For example, any impacts arising from delaying J12 improvements to beyond 2040 and implementing the Charfield scheme rather than a grade separated junction at J14?
Q15: Are there any additional local issues or impacts to both the strategic and local road networks that have arisen because of the updated evidence base that need to be addressed?

Q16: In your view are there any additional evidence base studies or transport modelling that should be undertaken to inform this Examination? If yes, then please explain what and why it is necessary.

14. We note that National Highways have requested additional transport evidence in relation to a recent planning application submitted to Stroud District Council on the Sharpness site allocation (PS36), including additional traffic modelling.

Q17: What is the nature of this additional transport evidence requested? What additional traffic modelling will be carried out? In your view, is this issue relevant to the Examination and the soundness of the Plan? Are there any other evidence base studies or transport modelling that need to be undertaken?

Responses

15. We would like responses to our questions from the organisations set out in paragraph 1 above by 17:00 on Tuesday 5 May 2026. If you require clarification of any of the above points, please contact us via the Programme Officer.

Yours faithfully

Victoria Lucas and Yvonne Wright

Inspectors appointed to examine the Stroud District Local Plan Review

05/03/2026

Examination Library

Update from the Programme Officer 02.03.2026

ID-021 Letter from the Inspectors 18 February 2026

Stroud District Local Plan Review Examination
Inspectors: Victoria Lucas LLB MCD MRTPI and
Yvonne Wright BSc (Hons) DipTP MSc DMS MRTPI
Programme Officer: Charlotte Glancy
Email: [email protected]
Tel: 07519 628064
____________________________________________________
Ms Kathy O’Leary
Chief Executive
Stroud District Council
Sent by email
18 February 2026
Dear Ms O’Leary
Stroud District Local Plan Review Examination

1. We write further to your letter dated 7 November 2025. Apologies for the delay in responding, however, unfortunately, we have both been out of the office.

2. In the light of your comments and in order for us to decide how best to take forward the examination we intend to undertake a limited consultation exercise on the most recent additional SRN capacity assessments undertaken by National Highways (June 2025) and publish additional questions regarding this evidence before the end of March 2026. As this issue relates to focused technical evidence, we intend to invite responses only from National Highways, Gloucestershire County Council and South Gloucestershire District Council at this stage, along with Stroud District Council. Therefore, we do not envisage accepting responses from any other interested party on this matter at this time.

3. This consultation exercise will be via an exchange of written evidence. We feel that is the most appropriate way forward, at this stage, due to the technical nature of the evidence. It will also be sufficient to enable us to understand the positions of the respective parties. We will of course keep under review the need for an oral hearing session should we have further questions relating to the evidence following the completion of this written exchange.

4. We will therefore write to you again before the end of March setting out our additional questions along with a timescale to submit responses to us. If you have any queries on this matter in the interim please let us know.

Yours sincerely,

Victoria Lucas and Yvonne Wright

Inspectors appointed to examine the Stroud District Local Plan Review

17/12/2025

SDC reply to the Inspectors 11:12:2025

Ms Lucas and Ms Wright
The Planning Inspectorate
Temple Quay House
2 The Square
Temple Quay
Bristol
BS1 6PN
7 November 2025

Dear Ms Lucas and Ms Wright

Re: Stroud District Local Plan Review Examination – Your Letter of 09 October 2025

Thank you for your letter of 9 October 2025, setting out your position regarding the Stroud District Local Plan Review Examination.

We have carefully considered the points raised. While we acknowledge the complexities involved, we must formally record our strong disagreement with the conclusion that plan withdrawal is the most appropriate way forward. We believe this conclusion is based on a flawed understanding of national policy, guidance and misunderstandings of fact, leading to flawed conclusions, which underestimate the plan's robustness and the Council's capacity to resolve the remaining matters efficiently.

1. Assessment of Transport Evidence

We note your conclusions regarding the need for extensive additional transport modelling, with which we disagree. We are concerned that these conclusions appear to be based on an incorrect technical interpretation of the highway evidence, an area which is the statutory responsibility of the local highway authority (Gloucestershire County Council) and the expert domain of National Highways. The Council's view is that the need for any additional transport modelling, aside from the scale of further work is questionable. In our view, the evidence base as it stands provides a sufficient foundation for the Examination to proceed to a hearing session where these specific technical matters can be properly tested and understood by the relevant parties.

2. Housing Delivery and Trajectory

Your letter suggests that potential deletion of certain site allocations would create a soundness issue regarding housing need. We are disappointed at this inference, as the highways evidence now accepted by National Highways clearly demonstrates the draft Plan's ability to meet the district's identified housing needs in a deliverable manner. The only question on the deliverability of the housing trajectory has been the need for and timing of motorway junction improvements, and the level of housing which could be delivered in advance of the junction improvement schemes. This is a matter in respect of which National Highways is the statutory consultee. The evidence on this front has been accepted by National Highways. Their acceptance is set out in the modelling reports. If the Inspectors have concerns over whether this represents National Highways’ formal position, this could be easily addressed through correspondence or clarified at a hearing session.

3. Proposed Timetable and Delay

Your view that a further 12-month pause is necessary, leading to an adoption date no earlier than 2027, appears to assume that additional detailed strategic modelling scenarios are needed. This is refuted by the Council and has not been requested by any of the Highways Authorities. The issues cited, including the local highway mitigation measures, are already identified and programmed within already submitted Infrastructure Delivery Plan (IDP). We are concerned that you are conflating matters to be addressed through the planning application process with those which are required to determine the soundness of the draft Plan. For example, it is unclear why you raise matters of the ongoing assessment of the Sharpness planning application by National Highways, despite the fact that National Highways itself has already set out its position on the impacts at J14 without needing that additional assessment itself.

We are confident that, with a focused hearing timetable, the remaining matters could be resolved within a much shorter, more reasonable timeframe without the need for such a protracted delay.

4. Mitigation for Local Highway Impacts

We note your concerns regarding impacts on the local highway network. We believe that you have misinterpreted the clarifications provided within the National Highways modelling reports on the scope of those studies. It is right and proper that National Highways highlights that it has not considered the road network for which it is not responsible. However, these issues are not new; they have been anticipated and are addressed by committed mitigation measures within the IDP, which falls under the jurisdiction of Gloucestershire County Council and South Gloucestershire Council, for example, the fact that the B4059 junction adjacent to J14 will experience capacity issues without mitigation. The mitigation in response is identified as a scheme within the IDP and has already been established through the evidence base.

What is also already clear is that the market is driving forward this draft plan with the Highways Authorities, in stark contrast to your conclusions. Strategic allocations such as Cam and Sharpness are using the approach we have agreed with highways partners and are assessing the local road network impacts as envisioned and set out in the IDP through the planning application process. This is not a matter to delay the local plan or for Examination scrutiny.

5. the ministerial direction on flexibility and statutory requirements

We note your position that " we still consider that withdrawal of the Stroud District Local Plan Review from Examination is the most appropriate way forward." This position appears inconsistent with the clear direction from the Minister of State for Housing and Planning, Matthew Pennycook, in his letter of 9 October 2025. The Minister emphasises that it is "critical that Inspectors approach examinations of current system plans with the appropriate degree of flexibility" and states unequivocally that "where plans are capable of being made adoptable, I want Inspectors to seek to do so in the examination process."

Specifically, the Minister welcomes that "in some cases Inspectors are already exercising a degree of flexibility to expedite adoption of local plans," citing "pragmatic decisions to proceed toward adoption in instances where a five-year housing land supply cannot be evidenced at the point of adoption but where the plan significantly boosts supply and still meets housing needs over the plan period."

This draft Plan is precisely such a case. It seeks to significantly boost housing supply, meet identified need in full, and is capable of being made adoptable. As we have maintained, we believe that your residual concerns could and should be addressed through an Examination hearing session.

Conclusion

We remain firmly of the view that all outstanding matters are either resolved or capable of resolution, primarily through addressing the misunderstandings that appear to underpin your current position in relation to policy, guidance, and factual interpretation. These are matters that would benefit from the clarity and scrutiny afforded by a further hearing session.

In our opinion, discontinuing the draft Plan prior to holding such a hearing would be a disproportionate and unnecessary step. We consider that the appropriate and proper course of action is to continue the Examination through the established hearing process, enabling the updated evidence to be fully considered.

We therefore respectfully urge you to reconsider your position.

Should you decide not to revise your position, we can confirm that Stroud District Council will not be withdrawing from the Examination. In that event, we request that you proceed to issue a full report in accordance with the Planning Inspectorate’s Examination Procedural Guide, including clear and reasoned justification for any recommendation of non-adoption.

Section 20(7A) of the Planning and Compulsory Purchase Act 2004 imposes a statutory duty to provide reasons for any recommendation of non-adoption. The Procedure Guide for Local Plan Examinations also sets the expectation that Inspectors will provide reasoned judgements for their conclusions and recommendations.

We ask that you revisit the policy, guidance, and factual misunderstandings outlined in your latest letter. If these are repeated in your final report, there is a risk that the report could be open to legal challenge. In our view, convening a hearing to address these matters would help to avoid or mitigate that risk prior to the publication of your report.

In light of clear ministerial direction, we also request that your final report explicitly sets out why adoption of the draft Local Plan, alongside a commitment to an early review, does not represent the flexible and pragmatic approach advocated by the Minister. Furthermore, we ask that you explain how non-adoption better serves the Government’s objective of significantly boosting housing supply, compared to adoption with early review. This approach, which we have consistently advocated, would also provide a platform for securing funding to address local infrastructure needs. Withdrawing the plan and starting a new plan would not be a quicker process or help the Council or the Governments objectives, as a new plan will take at 30 months under the new system. This would result in Stroud having no adopted up to date local plan until 2029 at the earliest. To date, the Council has not received any reasoning that addresses this critical issue.

We therefore request a report that fully and properly addresses these key matters and makes recommendations on all aspects of the draft Plan that have been considered through hearings and written representations, clearly setting out what you find sound and unsound.
This is imperative to allow the Council to move forward and consider a new local plan and the issues involved.

Given the Government’s stated intention to accelerate housing delivery through the planning system, we would be grateful if you could confirm either your reconsideration of the position or the expected timescales for issuing your report. This would support a more open and transparent process for all parties involved.

Yours sincerely

Kathy O’Leary Chief Executive

"The council fundamentally disagrees with the inspectors' interpretation of the new evidence, and will be responding for...
10/11/2025

"The council fundamentally disagrees with the inspectors' interpretation of the new evidence, and will be responding formally in due course," Ms Turner said.

Stroud District Council has been told to withdraw a major housing plan by government inspectors.

05/11/2025

An Inspector calls

The Inspectors have contacted Stroud District Council.
See below

Stroud District Local Plan Review Examination
Inspectors: Victoria Lucas LLB MCD MRTPI and
Yvonne Wright BSc (Hons) DipTP MSc DMS MRTPI
Programme Officer: Charlotte Glancy
____________________________________________________
Ms Kathy O’Leary
Chief Executive
Stroud District Council
Sent by email
09 October 2025
Dear Ms O’Leary
Stroud District Local Plan Review Examination

1. Thank you for your letter dated 11 July 2025. We have carefully considered its contents and are now writing to provide our response.

2. Firstly, we would like to acknowledge the progress made through the joint working between Stroud District Council (SDC) and National Highways (NH) and the updated evidence reports submitted. This is a positive step and represents a good foundation on which to resolve the concerns we have highlighted throughout this Examination regarding the impacts of planned growth arising from the Plan on the strategic road network.

3. In the interests of clarity, the NH reports that we refer to in our letter are: M5 J12 Stroud District Local Plan Capacity Assessment June 2025;
M5 J13 Stroud District Local Plan Capacity Assessment June 2025; M5 J14 Stroud District Local Plan Capacity Assessment June 2025. These reports are available to view on the Examination website. Whilst progress has undoubtedly been made, there remains several key concerns which we outline below.

4. The updated evidence published by NH indicates that the M5 J12 improvement would need to be operational and open to traffic by 2030 to accommodate planned growth arising from the Plan. However, if several site allocations were excluded (specifically G1 (south of Hardwicke), G2 (Land at Whaddon), and PS30 (Hunts Grove Extension) then there would be no need for mitigation to be provided at J12 until 2040. Planned growth can be accommodated within J13 in line with the scheme identified in the Infrastructure Delivery Plan and this reflects our understanding throughout the Examination process.

5. We understand that NH has accepted an interim scheme at J14 in connection with the Charfield planning application and this would allow for all planned growth arising from the Stroud Plan to be accommodated at J14 without the need for a grade separated junction to be provided.

6. In summary, it appears that NH has updated its position on J12 and J14 (although we have yet to receive formal confirmation directly from NH regarding this). Nevertheless, the updated evidence raises several potential soundness issues that we would need to consider. Not least, the deletion of several housing allocations and the implications of that for the extent to which the plan provides for meeting the identified housing need for the district. This work would need to be subject to a public consultation exercise and further discussion during a subsequent hearing session.

7. NH’s reports state that it has not considered any impacts of congestion on the local highway network and highlight that this needs to be brought to the attention of Gloucestershire County Council (GCC) and the relevant district councils. Whilst noting your comments on the point, we consider that the impact of planned growth on the local highway network is likely to be an important consideration in assessing the soundness of the plan. It may be that previous agreements existed between SDC, GCC and other relevant neighbouring Local Planning Authorities that local congestion issues could be dealt with via the planning application process. However, any such agreements were reached prior to the publication of the recent NH reports. The situation has since changed following the production of this latest evidence and this is a matter that would require further public consultation with relevant parties.

8. Throughout the reports the impact of traffic growth on the local highway network has been flagged as a concern and described as ‘significant’. For example, the J14 NH report highlights that whilst the interim scheme would satisfy NH’s interests as regards J14 capacity, it would ‘result in significant adverse impact on the A38 and B409 local highway network’.

9. The J12 NH report also states that any planned improvements at the Cross Keys roundabout may result in the J12 improvement scheme being required earlier. This is an issue that also would need to be discussed further so that we are able to fully understand any implications arising.

10. The modelling undertaken to support the Plan’s evidence base was undertaken on the basis that the junction mitigation schemes for J12 and J14 would be delivered during the Plan period. If those mitigation schemes are not going to be provided, then the assumptions underpinning the traffic modelling will need to be revised and further evidence will need to be produced so that the impacts of planned growth on the local highway network can be understood. It may well be that it would be appropriate to deal with this issue through the planning application process. However, currently there is insufficient evidence available for us (as well as relevant interested parties) to understand the full impact of planned growth on the local highway network without the delivery of the motorway junction improvements. Any work produced would also need to be consulted on and then subsequently discussed at future hearing sessions.

11. In relation to the need for further evidence to be provided, we note that NH have requested additional transport evidence in relation to a recent application submitted to SDC on the Sharpness site (PS36), to include additional traffic modelling. Whilst the consideration of that application is separate to the Examination it is likely that the evidence may well be relevant. We would therefore wish for any updated relevant evidence to be submitted to the Examination for our consideration. This would lead to further delay and the potential need for subsequent public consultation and discussion during a hearing session.

12. Overall, the issues arising from the recent NH reports would require the production of additional transport modelling, further public consultation, the production of a summary of representations and discussion at future hearing sessions. This would all clearly have time implications arising in further delays to the Examination process. Based on the experience of the Examination to date we would expect this process to take approximately 12 months to complete and therefore another pause in the Examination to accommodate this would be necessary.

13.Added to that, when we first wrote to SDC back in 2023 we highlighted the risk that if the Examination were to be prolonged that other evidence base documents would become out of date and would be likely to need updating. Looking through the Examination library there are several key pieces of evidence that were produced some years ago, and we would require these to be reviewed by SDC to determine whether they required an update. The implications of any updated evidence on the Plan would also need to be carefully considered.

14.Accordingly, whilst we held some hearing sessions during 2023, should relevant evidence require updating it would be necessary to hold these sessions again to ensure that the most up to date evidence has been considered. For example, hearing sessions on housing and employment need and requirement and the site allocations. There are also several hearing sessions that have yet to take place as a consequence of the pause in the Examination. Overall we envisage this could well be tantamount to starting the Examination of the Plan again.

15.As previously stated, the Plan was submitted by SDC to the Planning Inspectorate for Examination on 25 October 2021 and is being examined under the provisions of the 2021 National Planning Policy Framework (NPPF) that were in place at that time and the transitional arrangements set out in revisions to the NPPF since then. Even if the Examination were to proceed following another pause of significant length to undertake the additional processes that we have described;
the Plan would likely not be adopted until sometime during 2027. Moreover, given the likely housing requirement figure of this plan if it were to be adopted, the requirements of paragraph 236 of the transitional arrangements of the December 2024 NPPF mean that the Council would be expected to begin work on a new plan under the revised plan-making system as soon as the relevant procedures are brought into force in order to address the shortfall in housing need.

16.Whilst in these circumstances it might be beneficial to continue with the Examination if the plan were likely to be adopted in the next few months, we consider that it is not appropriate when its likely adoption would not occur until 2027.

17. For the reasons outlined in this letter, and our previous letters, we remain strongly of the belief that given the significant length of time that has already elapsed in this Examination, it would not be in the best interests of delivering the homes required in Stroud district by agreeing to further prolong the Examination of the current plan

18.Whilst we have very carefully considered the contents of your letter and have reviewed our previous conclusions in the light of them, unfortunately, for the reasons detailed above, we still consider that withdrawal of the Stroud District Local Plan Review from Examination is the most appropriate way forward.
Yours sincerely,

Victoria Lucas and Yvonne Wright

Inspectors appointed to examine the Stroud District Local Plan Review

https://www.stroud.gov.uk/media/zqclzmny/id-020-stroud-letter-09-october-2025.pdf

Address

Gloucester
GL27NT

Alerts

Be the first to know and let us send you an email when Wisloe Garden Village Plan, why it is WRONG posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Organisation

Send a message to Wisloe Garden Village Plan, why it is WRONG:

Share