Dundonald Playing Field Residents

Dundonald Playing Field Residents We are a number of residents who are very unhappy about the way the field has been left .

We had a response from SAC earlier about how the work is progressing on the field. They confirmed the following:1. Site ...
06/03/2026

We had a response from SAC earlier about how the work is progressing on the field. They confirmed the following:

1. Site is soft at the moment making progress more difficult
2. Crates are programmed for Monday of next week
3. Contractor hopeful to be completed 27th March

Work progressing well considering the weather. Let’s hope the £340,000 ‘investment’ by South Ayrshire Council aka Counci...
03/03/2026

Work progressing well considering the weather. Let’s hope the £340,000 ‘investment’ by South Ayrshire Council aka Council Tax payers, works. This was scheduled to be completed by this time last year

Update on the work. Hopefully it will be worth the effort and money spent by SAC.Unfortunately, the rest of the field is...
26/02/2026

Update on the work. Hopefully it will be worth the effort and money spent by SAC.

Unfortunately, the rest of the field is like a quagmire and full of ruts. Wonder how that will finish up?

Progress seems to be ongoing
25/02/2026

Progress seems to be ongoing

More photos of what's happening on the field today.Check out the size of the drains being put in
20/02/2026

More photos of what's happening on the field today.
Check out the size of the drains being put in

Photos of the field today.
19/02/2026

Photos of the field today.

Miracles do happenThis is the field this morning
17/02/2026

Miracles do happen
This is the field this morning

After five years since the initial issues arose, work is finally scheduled to begin on the flood mitigation measures.Thi...
16/02/2026

After five years since the initial issues arose, work is finally scheduled to begin on the flood mitigation measures.

This marks a significant step forward for the community, which has endured considerable disruption and uncertainty throughout this protracted period. The commencement of these works brings renewed hope that the persistent problems caused by the previous modifications to Dundonald Playing Field may at last be addressed.

Over a year ago, all parties decided to progress with an option delivered by Atkins (SAC Civil Consultants). However, SAC brought back an option that had previously been discounted, against the wishes of those involved. This decision delayed works by a year. The residents requested technical information behind that decision, but none was provided to justify the delay.

You all might be interested to know that through Freedom of Information requests made by residents, it revealed that an eye watering £340,000 of Council Tax payers’ money has been spent to restore the field and address flooding issues, with further expenditure anticipated by SAC for additional works.

Time will tell if the flood mitigation project is successful. The community, having endured years of disruption and uncertainty, now waits to see whether the measures implemented will truly resolve the ongoing issues caused by previous modifications to Dundonald Playing Field.

The outcome of this project will be closely monitored, as residents hope it will finally deliver the long-awaited relief and reassurance that the area is once again protected from flooding.

This experience highlights an important lesson for any future attempts by South Ayrshire Council to transfer assets to community groups. In this instance, a full and thorough due diligence exercise appears not to have been carried out on the financial and engineering capabilities prior to the asset lease.

It is essential that robust evidence is provided to demonstrate that community groups possess the necessary skills and resources to manage valuable assets effectively. Such diligence will help ensure that transfers deliver positive outcomes for the wider community, rather than benefitting only a select few. By taking these precautions, the risk of repeating a situation like this can be significantly reduced, safeguarding community interests and preventing further issues.

We thank everybody for their continued support during this unfortunate time.

For those who are not up to speed with the issues, we enclose a few photos of the damage done to the field

13/02/2026

AT LONG LAST

Five years have come and gone.

This should have been completed last September.

Hopefully this time, South Ayrshire Council are finally getting round to completing the flood prevention project.

We got this earlier today from South Ayrshire Council:

This morning the prestart meeting took place between the contractor , ARA and South Ayrshire Council in relation to the flood prevention works to be installed within Dundonald Recreation Ground .

The contractor will be coming on site next week and an anticipated completion schedule of 4-6 weeks depending on weather.

07/02/2026

We got this 'response' from SAC yesterday. It read:

The contractor is currently finalising the programme, including lead-in times for materials (in particular the rainwater cells). It is not possible to commit to timescales until this process is complete, but a finalised programme will be communicated as soon as possible.

More delays......................................

02/02/2026

Communication with South Ayrshire Council

Since our last post, we have consistently reached out to South Ayrshire Council seeking updates regarding the progress of the field. Despite our enquiries, the Council has remained quite reticent, choosing not to disclose any information pertaining to the installation of the swale. So much for transparency !!

12/12/2025

After much correspondence back and forth with SAC over the past few weeks, we can provide an update regarding the capital reprofiling and the financial adjustments relating to the delayed field works.

With respect to the swale project, SAC have now confirmed that the necessary funding is securely allocated within the programme that was previously presented to Council.

Following the approval granted yesterday, Council Officers were promptly notified and consequently, they have today issued an instruction to Ayrshire Roads Alliance to proceed with the necessary actions.

We hope to update more before the holiday period.

Address

Dundonald

Website

Alerts

Be the first to know and let us send you an email when Dundonald Playing Field Residents posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Share