I know the ongoing road closures and construction projects in Ward 7 have already been frustrating for many of our residents. Unfortunately, we’re still in the early stages of what will be several years of significant infrastructure improvements throughout our neighborhoods.
Between sewer separation projects, waterline replacements, and other upgrades, we’re going to see plenty of orange cones, detours, and torn-up streets in the years ahead. It’s not always going to be pretty, and I know these disruptions can make everyday life more difficult.
But here’s the good news! These projects represent substantial investments in our neighborhoods, our homes, and the infrastructure that will serve our community for decades to come. Much of this work happens underground, so we won’t always see the improvements, but they’re incredibly important.
The city works to coordinate construction schedules and contractors to minimize disruptions, but with this much work happening, there are bound to be some bumps along the way. Please pay attention to posted signs, parking restrictions, and detours, and use extra caution in construction areas.
And please keep communicating! If you’re experiencing specific issues with access, parking, safety, or anything else related to construction, reach out to the city or contact me directly. We need to know about problems so they can be addressed.
So, while I won’t officially say “buckle up, buttercup,” I think we can all agree that a little patience, flexibility, and a healthy sense of humor are going to come in handy over the next few years!
There’s a lot of work ahead, but I’m genuinely excited about what these investments mean for the future of Ward 7. Our neighborhoods are worth investing in, even when the process gets a little messy.
The city’s latest construction update is shared below.
ROAD CLOSURE UPDATE
Road: WOODS AVENUE
Location: Between Rugg Avenue and Moull Street
Beginning: September 21, 2026
Ending: ~Thanksgiving
Other Details: Rolling Closure: the previous section will be opened to traffic prior to closing the next section. Work will occur from north to south with only one intersection closed at a time.
Rugg Avenue is expected to open and Jefferson Road is expected to close Wednesday, October 21st
See Attached Map for Details
Project: 16 North Sewer Separation Project Phase 1
Project Website: https://www.newarkohio.gov/water-wastewater-construction-projects/ -toc__heading-anchor-8
For: Waterline Replacement
Questions? Please Call: (740) 670-7946
For daily/weekly construction updates, visit our page: “City of Newark Ohio Construction Updates” https://www.facebook.com/CityOfNewarkOhioConstructionUpdates/
Dates Subject to Change