Restore, Renew, Rejoice Project Update No. 7 | 19 April 2026
Work continues on schedule, with strong progress across the site.
The oil tank has now been removed, and a new slab has been laid for the LPG tank, which will be screened by forthcoming planting.
Electricity ducts and water pipework for the radiators are fully in place.
Beam and block flooring has begun in key areas, including over the boiler room and the sunken grave at the rear of the north aisle.
Next up: installation of the deep insulation layer, which will house the underfloor heating system.