05/06/2026
A joint site inspection was conducted to assess the progress of works at Tali Shedra Road Widening, Dungmang Chiwog Road Improvement, and Leyleygang to Tsheldang Zampa Farm Road Construction.
The 1.5 km Tali Shedra road widening work is progressing well with steady advancement and no major issues observed.
At Dungmang Kamjong Chiwog road improvement (HICDP-ll) work has reached 1.2 km out of the total 2.0 km and is proceeding as per schedule and It will continue till 21/09/2026.
For the Leyleygang to Tsheldang Zampa Farm Road (HICDP-l), first cutting has been completed for 5.64 km and back cutting for 5.45 km, Contract End Date on 18/08/2026.
Overall, work progress at all three sites is good, and the inspection team advised the contractor to continue works as planned while maintaining quality standards throughout ex*****on.