𝗧𝗲𝗿𝘃𝘂𝗿𝗲𝗻 𝘀𝗲𝘄𝗲𝗿 𝘄𝗼𝗿𝗸𝘀 𝗲𝘅𝘁𝗲𝗻𝗱𝗲𝗱 𝘁𝗼 𝟮𝟵 𝗝𝗮𝗻𝘂𝗮𝗿𝘆 𝟮𝟬𝟮𝟳. By Dafydd ab Iago. Drivers in Tervuren face more than three months of detours after the town hall extended sewer works on the Vestenstraat and Louis Buelenslaan until Friday 29 January 2027.
The works, with an estimated cost of €1.56 million excluding VAT, were due to finish on 18 December, so they now run six weeks longer. Mayor Thomas Geyns (Voor Tervuren, Anders) and his aldermen approved the revised traffic order on 5 October. It replaces a July order and applies from Tuesday 13 October. The town’s notice does not give a reason for the extension.
In central Tervuren, contractor HENS is laying a new sewer system and rebuilding the whole carriageway. The Vestenstraat is closed to motor traffic between the Jezus Eiklaan and the Jef Coosemansstraat, and so is the Louis Buelenslaan.
One section is already open again. Work on the Vestenstraat between the Brusselsesteenweg and the Jef Coosemansstraat, including the junction with the Jef Coosemansstraat, is complete, so traffic can now be sent that way. The town says this makes the school area safer, and the new route has been agreed with bus operator De Lijn.
Motorists coming from the Jezus Eiklaan must follow a diversion via the Hippolyte Boulengerlaan and the Jef Coosemansstraat to the Vestenstraat, which becomes one-way towards the Brusselsesteenweg. Cyclists are diverted along the same streets in both directions.
Parking is banned across the work zone, in the Hippolyte Boulengerlaan, on part of the Jezus Eiklaan and at numbers 17 to 19 of the Jef Coosemansstraat, to keep buses and traffic moving.
𝗧𝗿𝗮𝗳𝗳𝗶𝗰 𝗠𝗲𝗮𝘀𝘂𝗿𝗲𝘀 𝗳𝗿𝗼𝗺 𝟭𝟯 𝗢𝗰𝘁𝗼𝗯𝗲𝗿 𝟮𝟬𝟮𝟲 𝘁𝗼 𝟮𝟵 𝗝𝗮𝗻𝘂𝗮𝗿𝘆 𝟮𝟬𝟮𝟳
All measures apply from Tuesday 13 October 2026 to Friday 29 January 2027.
ChangeWhereWhat it means
Full closure to motor trafficVestenstraat between Jezus Eiklaan and Jef Coosemansstraat; Louis BuelenslaanNo through route for cars. Pedestrians always get a safe passage.
Finished section used as diversionVestenstraat between Brusselsesteenweg and Jef Coosemansstraat, including the junction with Jef CoosemansstraatWorks complete. The town says it makes the school area safer; route agreed with De Lijn.
One-way trafficVestenstraat between Jef Coosemansstraat and BrusselsesteenwegTraffic flows only towards Brusselsesteenweg.
Diversion for carsFrom Jezus Eiklaan via Hippolyte Boulengerlaan and Jef Coosemansstraat to VestenstraatFollow the signed detour; expect longer journeys.
Diversion for cyclistsJezus Eiklaan, Hippolyte Boulengerlaan, Jef Coosemansstraat, VestenstraatSame streets, in both directions.
Parking ban: work zoneWhole work zone, both sides of the roadNo parking for the length of the works.
Parking ban: busesJef Coosemansstraat, numbers 17 to 19Keeps De Lijn buses moving.
Parking ban: traffic flowHippolyte Boulengerlaan; Jezus Eiklaan between Vestenstraat and Hippolyte BoulengerlaanKeeps the diversion flowing.
Advance warning signsTervurenlaan x Brusselsesteenweg; Hippolyte Boulengerlaan x Jezus Eiklaan; Ortar De Pauwstraat x Jezus Eiklaan; Duisburgsesteenweg x RinglaanDrivers are warned before they reach the closure.
Contractor’s duties (HENS)Whole work zoneWritten notice to residents and traders in Dutch at least 5 working days ahead; homes and shops stay accessible; at least 3.5 metres of road open outside approved closures; closed roads reopened to emergency vehicles within 5 minutes; a Dutch-speaking person on site.
Source: decision of Tervuren’s college of mayor and aldermen, 5 October 2026.
𝗔𝘀𝗽𝗵𝗮𝗹𝘁 𝗪𝗼𝗿𝗸𝘀, 𝟮𝟬–𝟮𝟯 𝗢𝗰𝘁𝗼𝗯𝗲𝗿
Asphalt resurfacing is planned on the Bleuckeveldlaan, Ringlaan, Hertenbergstraat, Veeweidestraat and Hondsbergen, weather permitting. Between 7am and 6pm homes in the work zones cannot be reached by car. They can be reached again after the old asphalt is removed, and traffic is fully allowed once the new layer has hardened.